6. Good product and Reject

Table of Contents

6. Good product and Reject

In this example:

  • Shift time:                                         500 min
  • Total entered activity time:         100 min
  • Not registered:                                400 min
  • Max output:                                     100min x 1000 pcs = 100.000 pcs
  • Set speed                                          800 pcs/min
  • Expected output:                            100min x 800 pcs = 80.000 pcs
  • Actual Output:                                 45.000 Good Product – 5000 Rejects

Result:

  1. Availability 20% (100min/500min)
  2. Performance: 50% (Actual output / Maximum Output)
  3. Quality: Good Product / (Good+Rejects) = 90%
  4. OEE = 20% x 50% x 90% = 9%