8. Two sorts of Reject with one Product

Table of Contents

8. Two sorts of Reject with one Product

In this example:

  • Shift time:                                        500 min
  • Production  time:                           100 min
  • Waiting:                                            400 min
  • Max output:                                    100 min x 1000 pcs = 100.000 pcs
  • Set speed                                         800 pcs/min
  • Expected output:                            100 min x 800 pcs = 80.000 pcs
  • Actual Output:                                 50.000 Good Product, 6.000 Rework, 4.000 Sub Spec

Result:

  1. Availability 20% (100min/500min)
  2. Performance: 60% (Actual output / Maximum Output)
  3. Quality: Good Product / (Good+Rejects) = 83%
  4. OEE = 20% x 60% x 83% = 10%