Table of Contents

What if Shifts/Batches run >24 Hrs

If the time format -defined at the machine- is [HH:MM] than the maximum duration of a calculation is 24:00 hr

If you need longer calculations than 24 hrs, select [d.hh:mm] instead of [HH:MM] in master data ‘Machines’, field ‘Time Format’.

With this format, the number of days will be visible. Durations of activities however can still be in another format.

The durations of activities however can still be in any other format you like.